Total E&P Nederland : Local subsidiary
of the group. 2002/2003 - One year assistance contract
including 3 months on the yard and 3 months offshore in
the North Sea : K5PK Project. Gas compression platform
construction, installation and integration to the existing
K5 Complex in the Dutch sector of the North Sea. ►
Onshore :
Planning and resources audit of the contractor and
corrective actions recommendations. Preparation and
monitoring of the precomm-commissioning schedule. Analysis
and readjustment of the installation, Hook-up and start-up
schedule.
►
Offshore :
Preparation, implementation and
monitoring of the progress measurement system for the
revamping. Misc. Reporting. Preparation and monitoring of
the daily corrective actions plan.
►
Contract Close-out Dossier :
Punch
lists gathering and sequencing. Offshore mobilisation
analysis and ratios calculations. Project Close out report
preparation. Lessons learned and project documentation
archiving.

Technip-Coflexip Group : 2001 - 5 months assistance Contract with
Technip USA in Houston, TX : DPlanning strategy definition,
Schedules and progress measurement system set-up for the execution
of the F.E.E. Phase for the Bengela-Belize-Tomboco Development Project:
Preliminary Design for a Drilling and Production Offshore Platform
in the Gulf of Angola. Client Consortium Leader: Chevron Oil
Company.
2001 - 4 months assistance Contract
with
Technip
France in Paris: PPlanning package,
Schedules and progress measurement system set-up
for the execution of the Engineering and
Procurement Phase for the Soroosh-Nowrooz Field
Development Project : EPCI project for 7 Offshore
Platforms (2 wellheads, 3 production and 2 living
quarters) in the Iranian part of the Persian Gulf.
Client: SHELL.

GlaxoWellcome
France (now GSK) : Planning Team set-up and
management for the realization of a continuous
progress and rationalisation project "Strategic
Master Plan" : work organization, procedure &
software implementation, level 4 & 5 schedules
tailoring, coordination & progress collection,
reporting and communication with the UK Core Team
at
GlaxoWellcome
London.

RENAULT : Consulting mission : Planning
and project progress reporting procedures
implementation for several gear box development
projects at their different stages : research and
design phase, prototype construction and test
phase, industrialization & launching phase.
Centre Hospitalier Intercommunal de
Créteil : Organization, monitoring and
Coordination contract with French Health Ministry
for the construction of the hospital extension.
Preparation of planning and cost control procedures
for integration to the work subcontracts bid
packages. Preparation of progress report format.
Preparation of the level 1 overall project schedule
and financial program.
ELF Aquitaine : Consulting mission for the
implementation of quality assurance procedures
applied to the planning, progress reporting and
document control of COBO offshore platform project,
Angola.
SOFRESID / OTP : Expatriate for the EPCS contract
for the construction of 210 Km 16" pipelines and
export/receiving stations. Pertamina Company (Java
Island, Indonesia). Preparation of planning,
document control and equipment procurement progress
procedures. Preparation of document register and
level 2 detailed planning. Preparation of monthly
progress report format. Local staff education and
training.
TECHNIP : Several assistance missions
performed with the responsibility of the design and
then monitoring & update of various schedules,
of the preparation and implementation of project
control procedures, of the Integrated physical
progress measurement system setup, of the weekly
and monthly schedule and progress report
preparation and of the subcontractors &
partners progress audit.
► ADNOC: Onshore Gas Development Phase 1 Project
545 & Phase 2 Project 1219, Abu Dhabi, United
Arab Emirates : Gas processing plants and
associated facilities LSTK (Lump Sum Turnkey)
contracts carried out by Technip-Bechtel-CCC
consortium. Particularly in charge of sulphur
recovery units subcontract monitoring.
► Preparation of schedules and progress measurement
& monitoring procedures for several EPC bid
packages, mainly petrochemical projects.
► EPCS contract for the polypropylene plant at
Gielsenkirchen for DSM Company, Germany.
► TOTAL Co: Gas Plant reconstruction project for
the renewal of the la Mède refinery, France.
► PETROGAL, cracking complex project for the
extension of the Sines refinery, Portugal. LSTK
contract.
► NODCO, Penex/Molex isomerization unit LSTK
contract, for the Umm Saïd refinery expansion,
Qatar. Engineering & procurement phase.
Alsthom Oil
Services: : LNG/LPG Tanks Dismantling project
in Das Island, UAE, for AOS (Alsthom Oil Services).
Preparation of planning and cost control
procedures. Setup of WBS and OBS structures.
Drafting of level 1 planning (200 activities).
USSI
Ingénierie : Technical assistance to USSI
Ingénierie/SGN for the design and the
implementation of the MELOX project progress
measurement system. Nuclear fuel production and
waste reprocessing plants project.
SOGELERG /
AEROSPATIALE : Detailed construction schedules
of the industrial plants for the commercial
equipment for Airbus A330/A340 aircrafts.
SOGELERG / SNCF : design coordination and
scheduling & follow-up of the technical trades
for the construction of the Montparnasse-Pasteur
TGV train station, Paris.
KLÖCKNER MATEX : Design, procurement and
construction project of six clothing production
plants in the USSR. Coordination of design and
procurement. Scheduling of works and on-site
specialist assignments. Negotiation of specialist
mobilization and settlement of amendments with
equipment suppliers. Preparation and implementation
of procedure for parts replacement and services
performed under guarantee.
|
|